导读:(2)performance test run:the performance test shall extend continuously over a (_________) hour period.(3)two or more units:where the contract plant includes two or more individual process unitsfor which separate process performance guarantees are to be demonstrated,the performance test may be carried out individually on each of the unitsor simultaneously with any other unit or units.(4)buyer's personnel:the performance test shall be carried out by the
国际技术转让加设备进口合同,标签:技术开发合同,技术咨询合同,http://www.qz26.com
(2)performance test run:the performance test shall extend continuously over a (_________) hour period.
(3)two or more units:where the contract plant includes two or more individual process unitsfor which separate process performance guarantees are to be demonstrated,the performance test may be carried out individually on each of the unitsor simultaneously with any other unit or units.
(4)buyer's personnel:the performance test shall be carried out by the buyer's operatingpersonnel according to the instructions set forth in the supplieroperating manual and under the technical services of the supplier'sengineer.
(5)interruption of performance test due to supplier:if the performance test run is interrupted because of failure of thesupplier, the performance test shall be repeated. the results obtainedduring such an interrupted operation shall not be used for evaluation ofthe performance test.
(6)interruption of performance test due to buyer:if the performance test is interrupted because of failure of the buyerto comply with any of the conditions set forth in this appendix 5 (processperformance guarantees)and any other parts of the agreement or because ofimproper maintenance or operation on the part of the buyer,theperformance test shall be repeated but if it had been running for morethan _________ hours then the duration of the performance test before theinterruption may be credited to the performance test period and theresumed performance test will be continued for the remainder of theperformance test period.
(7)conditions for resumption:the conditions which have caused the interruption shall be correctedby the party who was responsible for the interruption. upon restoration ofthe steady and satisfactory performance test operating conditions, theperformance test shall be resumed.
(8)operating data:operating and analytical data recorded during the performance testshall be taken down by the buyer and made available to the supplier forevaluation.
(9)sampling and analysis:during the performance test, samples necessary for evaluation of theperformance of the contract plant shall be taken as often as the supplierand the buyer mutually agree.the samples shall include all streams which may be necessary to checkthe data from which the degree of compliance with the process performanceguarantees can be determined.the location and methods of sampling the streams shall be inaccordance with those as agreed between the parties hereto under paragraph4.1 (1)above.
(10)testing:testing of all samples shall be carried out by the buyer's laboratoryor an independent industrial laboratory acceptable to the parties heretoaccording to the analytical procedure as agreed between the parties heretounder paragraph 4.1 (1)above. the supplier's and the buyer's personnelmay have free access to the laboratory when the samples are tested and maycheck the test results.
4.4evaluation and report of performance test.
(1)evaluation of performance test data:evaluation of the performance test data including the operating andlaboratory data accumulated during, or as a part of, the performance testshall be done by the supplier within _________ days after the completion ofthe performance test.
(2)abnormal test data:any abnormal test data which is not compatible with other significantdata shall be ignored or the test data in question may be taken again ifpractical from the contract plant operating conditions.

上一页  [1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] [24] [25] [26] [27] [28] [29] [30] [31] [32] [33] [34] [35] [36] [37] [38] [39] [40] [41] [42] [43] [44] [45] [46] [47] [48] [49] [50] [51] [52] [53] [54] [55] [56] [57] [58] [59] [60] [61] [62] [63] [64]  下一页


Tag:技术合同技术开发合同,技术咨询合同合同范本 - 技术合同
【字号: 】 【打印】 【关闭
最新更新
推荐热门
联系我们 | 网站地图 | 财务资料 | 范文大全 | 求职简历 | 财会考试 | 成功励志
Copyright 二六求职资料网 All Right Reserved.
1 2 3 4 5 6 7 8 9 10