导读:25.3.3the buyer shall within seven (7)days after receipt of the supplier's notice issue such acceptance certificate.25.3.4if, within seven (7)days after receipt of the supplier' snotice, the buyer fails to issue the acceptance certificate or fails toinform the supplier in writing of the justifiable reasons why the buyerhas not issued the acceptance certificate, the contract plant there of shall be deemed to have been accepted as at the date of the
国际技术转让加设备进口合同,标签:技术开发合同,技术咨询合同,http://www.qz26.com
25.3.3the buyer shall within seven (7)days after receipt of the supplier's notice issue such acceptance certificate.
25.3.4if, within seven (7)days after receipt of the supplier' snotice, the buyer fails to issue the acceptance certificate or fails toinform the supplier in writing of the justifiable reasons why the buyerhas not issued the acceptance certificate, the contract plant there of shall be deemed to have been accepted as at the date of the supplier'ssaid notice.
article 26.delivery time guarantee
26.1delivery time guarantee the supplier guarantees that it shall deliver to the buyer;
(a)each such basic lot of the equipment within such corresponding time for delivery, as referred to in article 22.2.1 hereof and finallyfixed in the final delivery schedule pursuant to article 22.2.3 hereof,and
(b)each such basic item of the technical documents whose time fordelivery is guaranteed as specified in appendix 7-4 (time schedule)heretowithin the corresponding time for delivery specified therein,subject, however, to any extension of each such time for delivery towhich the supplier shall be entitled under article 37 (extension of timefor delivery)hereof.
26.2late delivery of equipment
if the supplier fails to deliver to the buyer any portion of the equipment included in such a basic lot within such corresponding time fordelivery, as specified in article 26.1 (delivery time guarantee)above orany extension thereof under article 37 (extension of time for delivery)hereof, the supplier shall pay to the buyer liquidated damages for eachsuch delayed portion of the equipment at the following rates for everyweek of delay, providing that fractions of four days or more shall becounted as one week and fraction(s)of less than four days shall beomitted:
(a)for the first four weeks of delay:_________ per cent (_________%)of the invoiced amount of the delayedportion of the equipment per week;
(b)for the second four weeks of delay following the first four weeksof delay:_________ per cent (_________%)of the invoiced amount of the delayedportion of the equipment per week;
(c)for the ninth and subsequent week(s)of delay:_________ per cent (_________%)of the invoiced amount of the delayedportion of the equipment per week;
such monies shall be paid as liquidated damages and not as a penalty.the total aggregate amount of such liquidated damages shall in no eventexceed _________ per cent (_________%)of the contract price for theequipment specified in article 12 (contract price and technical servicefee)hereof.
26.3late delivery of technical documents
if the supplier fails to deliver to the buyer any basic item of thetechnical documents specified in appendix 7-4 (time schedule)hereto whosetime for delivery is guaranteed under article 26.1 (delivery timeguarantee)above within the corresponding time for delivery specified inappendix 7-4 (time schedule)hereto or any extension thereof under article37 (extension of time for delivery)hereof, the supplier shall pay to thebuyer liquidated damages for each such delayed basic item of the technicaldocuments at the following rates for every week of delay, providing thatfractions of four days or more shall be counted as one week andfraction(s)of less than four days shall be omitted:
(a)for the first four weeks of delay:_________ percent (_________%)of the total design fee specified inarticle 12 (contract price and technical service fee)hereof per week;
25.3.3the buyer shall within seven (7)days after receipt of the supplier's notice issue such acceptance certificate.
25.3.4if, within seven (7)days after receipt of the supplier' snotice, the buyer fails to issue the acceptance certificate or fails toinform the supplier in writing of the justifiable reasons why the buyerhas not issued the acceptance certificate, the contract plant there of shall be deemed to have been accepted as at the date of the supplier'ssaid notice.
article 26.delivery time guarantee
26.1delivery time guarantee the supplier guarantees that it shall deliver to the buyer;
(a)each such basic lot of the equipment within such corresponding time for delivery, as referred to in article 22.2.1 hereof and finallyfixed in the final delivery schedule pursuant to article 22.2.3 hereof,and
(b)each such basic item of the technical documents whose time fordelivery is guaranteed as specified in appendix 7-4 (time schedule)heretowithin the corresponding time for delivery specified therein,subject, however, to any extension of each such time for delivery towhich the supplier shall be entitled under article 37 (extension of timefor delivery)hereof.
26.2late delivery of equipment
if the supplier fails to deliver to the buyer any portion of the equipment included in such a basic lot within such corresponding time fordelivery, as specified in article 26.1 (delivery time guarantee)above orany extension thereof under article 37 (extension of time for delivery)hereof, the supplier shall pay to the buyer liquidated damages for eachsuch delayed portion of the equipment at the following rates for everyweek of delay, providing that fractions of four days or more shall becounted as one week and fraction(s)of less than four days shall beomitted:
(a)for the first four weeks of delay:_________ per cent (_________%)of the invoiced amount of the delayedportion of the equipment per week;
(b)for the second four weeks of delay following the first four weeksof delay:_________ per cent (_________%)of the invoiced amount of the delayedportion of the equipment per week;
(c)for the ninth and subsequent week(s)of delay:_________ per cent (_________%)of the invoiced amount of the delayedportion of the equipment per week;
such monies shall be paid as liquidated damages and not as a penalty.the total aggregate amount of such liquidated damages shall in no eventexceed _________ per cent (_________%)of the contract price for theequipment specified in article 12 (contract price and technical servicefee)hereof.
26.3late delivery of technical documents
if the supplier fails to deliver to the buyer any basic item of thetechnical documents specified in appendix 7-4 (time schedule)hereto whosetime for delivery is guaranteed under article 26.1 (delivery timeguarantee)above within the corresponding time for delivery specified inappendix 7-4 (time schedule)hereto or any extension thereof under article37 (extension of time for delivery)hereof, the supplier shall pay to thebuyer liquidated damages for each such delayed basic item of the technicaldocuments at the following rates for every week of delay, providing thatfractions of four days or more shall be counted as one week andfraction(s)of less than four days shall be omitted:
(a)for the first four weeks of delay:_________ percent (_________%)of the total design fee specified inarticle 12 (contract price and technical service fee)hereof per week;
上一页 [1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [12] [13] [14] [15] [16] [17] [18] [19] [20] [21] [22] [23] [24] [25] [26] [27] [28] [29] [30] [31] [32] [33] [34] [35] [36] [37] [38] [39] [40] [41] [42] [43] [44] [45] [46] [47] [48] [49] [50] [51] [52] [53] [54] [55] [56] [57] [58] [59] [60] [61] [62] [63] [64] 下一页